Chips, data centers and power

The race, in steel and watts.

The biggest AI data centers and the power they draw, the chips inside them, who owns the computing power, what is being spent and who is pushing back, from open data and named sources.

  • 94AI data centers tracked by Epoch AI
  • 14.2 GWof computing power across them
  • 415 TWhused by all data centers in 2024, about 1.5% of the world's electricity
The biggest AI data centers

Where the power is drawn.

Power for the computing equipment (IT power), as Epoch AI estimates it from satellite images, permits and filings. Planned figures are Epoch's projections, not the owners' claims.

25 of the largest sitesHalo size: power now · ring: planned
Anthropic-Amazon New Carlisle, New Carlisle, Indiana, USA: 1,037 MW now, 1,925 MW plannedColossus 2, Memphis, Tennessee, USA: 946 MW now, 1,531 MW plannedMicrosoft Fairwater Atlanta, Fayetteville, Georgia, USA: 636 MW nowDayOne Nusajaya, Johor Bahru, Johor, Malaysia: 473 MW now, 473 MW plannedMeta Prometheus, New Albany, Ohio, USA: 471 MW now, 1,022 MW plannedDayOne Kempas, Kempas, Johor Bahru, Johor, Malaysia: 422 MW nowOpenAI Stargate Abilene, Abilene, Texas, USA: 421 MW now, 843 MW plannedMicrosoft Fairwater Wisconsin, Mount Pleasant, Wisconsin, USA: 369 MW now, 2,263 MW plannedGoogle Pryor (North), Pryor, Oklahoma, USA: 368 MW nowColossus 1, Memphis, Tennessee, USA: 340 MW nowGoogle New Albany, New Albany, Ohio, USA: 333 MW nowGoogle Columbus, Columbus, Ohio, USA: 303 MW now, 386 MW plannedAmazon Madison Mega Site, Canton, Madison County, Mississippi, USA: 284 MW now, 683 MW plannedCoreWeave Denton TX, Denton, Texas, USA: 262 MW now, 282 MW plannedBridge Data Centres MY06, Sedenak Tech Park, Johor, Malaysia: 243 MW nowAmazon Ridgeland, Ridgeland, Mississippi, USA: 228 MW now, 840 MW plannedVNET Bayin Ulanqab, Ulanqab, Inner Mongolia, China: 221 MW now, 700 MW plannedHuawei Horinger, Horinger (Hohhot), Inner Mongolia, China: 184 MW now, 346 MW plannedAlibaba Zhangbei, Zhangbei, Hebei, China: 169 MW now, 169 MW plannedMeta Hyperion, Holly Ridge, Louisiana, USA: under construction, 1,632 MW plannedOpenAI Stargate Shackelford, Shackelford County, near Abilene, Texas, USA: under construction, 1,400 MW plannedOpenAI Stargate UAE, Abu Dhabi, United Arab Emirates: under construction, 1,000 MW planned
Map positions are the nearest town's, not the site's. Waltham Cross, Stargate Michigan and Stargate Milam aren't on the map because we couldn't confirm a town position.
  1. 1Anthropic-Amazon New CarlisleAmazon · New Carlisle, Indiana, USA1,037 MW1,925 planned, Mar 17, 2028
  2. 2Colossus 2SpaceXAI · Memphis, Tennessee, USA946 MW1,531 planned, Q1 2027
  3. 3Microsoft Fairwater AtlantaMicrosoft · Fayetteville, Georgia, USA636 MW
  4. 4DayOne NusajayaOwner not stated · Johor Bahru, Johor, Malaysia473 MW
  5. 5Meta PrometheusMeta · New Albany, Ohio, USA471 MW1,022 planned, Q3 2028
  6. 6DayOne KempasOwner not stated · Kempas, Johor Bahru, Johor, Malaysia422 MW
  7. 7OpenAI Stargate AbileneOracle · Abilene, Texas, USA421 MW843 planned, Q4 2026
  8. 8Microsoft Fairwater WisconsinMicrosoft · Mount Pleasant, Wisconsin, USA369 MW2,263 planned, Q2 2028
  9. 9Google Pryor (North)Google · Pryor, Oklahoma, USA368 MW
  10. 10Colossus 1SpaceXAI · Memphis, Tennessee, USA340 MW
  11. 11Google New AlbanyGoogle · New Albany, Ohio, USA333 MW
  12. 12Google ColumbusGoogle · Columbus, Ohio, USA303 MW386 planned, Jul 1, 2027
  13. 13Amazon Madison Mega SiteAmazon · Canton, Madison County, Mississippi, USA284 MW683 planned, Mar 15, 2028
  14. 14CoreWeave Denton TXCoreWeave · Denton, Texas, USA262 MW282 planned, May 31, 2027
  15. 15Bridge Data Centres MY06ByteDance (likely) · Sedenak Tech Park, Johor, Malaysia243 MW
  16. 16Amazon RidgelandAmazon · Ridgeland, Mississippi, USA228 MW840 planned, Sep 29, 2028
  17. 17VNET Bayin UlanqabVNET · Ulanqab, Inner Mongolia, China221 MW700 planned, Q3 2027
  18. 18Huawei HoringerHuawei · Horinger (Hohhot), Inner Mongolia, China184 MW346 planned, Q1 2028
  19. 19Alibaba ZhangbeiAlibaba · Zhangbei, Hebei, China169 MW
  20. 20Google Waltham CrossGoogle · Cheshunt, Hertfordshire, UK88 MW

Still being built

Source: Epoch AI, AI data centers (CC BY 4.0), Oct 19, 2026. The list is the 20 largest by power now, plus the largest in China and the UK. Owner names are Epoch's. Epoch's figure for New Carlisle is an estimate; its last satellite reading was 910 MW in June.

The chips

What's inside, and how strong.

Each maker's AI chips, rated against Nvidia's H100 (H100 = 1) by Epoch AI. A rating of 2.5 means about two and a half H100s of computing power.

US

Nvidia

  1. H100Sep 20, 20221×
  2. H20 (China-market)Nov 9, 20230.15×
  3. H200Nov 18, 20241×
  4. B200Feb 15, 20252.53×
  5. B300Aug 22, 20252.53×
  6. Rubinno date given8.84×
Company-reported

Vera Rubin platform in full production.

“Vera Rubin, now in full production, was built to power exactly this moment.”

NVIDIA, Q2 fiscal 2027 results, Aug 26, 2026

US

AMD

  1. Instinct MI300XDec 6, 20231.32×
  2. Instinct MI308X (China-market)Dec 6, 20230.33×
  3. Instinct MI325XOct 10, 20241.31×
  4. Instinct MI350XJun 12, 20252.33×
  5. Instinct MI355XJun 12, 20252.54×
Company-reported

AMD says it launched the Instinct MI400 Series (MI455X, MI430X) and the MI350P; Helios rack-scale systems starting to ramp; Anthropic deal for up to 2 GW of MI450 Series GPUs (2026-07-22).

AMD, Q2 2026 results, Aug 4, 2026

US

Google (TPU)

  1. TPU v5pDec 6, 20230.46×
  2. TPU v6e (Trillium)May 14, 20240.93×
  3. TPU v7 (Ironwood)Nov 6, 20252.33×
  4. TPU v8iAug 2, 20265.1×
Company-reported

Ironwood, seventh-generation TPU: 4,614 TFLOPs FP8 per chip, pods of up to 9,216 chips.

“Ironwood represents a significant shift in the development of AI and the infrastructure that powers its progress.”

Google blog, Ironwood, Apr 9, 2025

US

Amazon (Trainium)

  1. Trainium1Oct 15, 20220.21×
  2. Trainium2Dec 3, 20240.66×
  3. Trainium3Dec 2, 20251.27×
China

Huawei (Ascend)

  1. Ascend 910BMar 17, 20220.19×
  2. Ascend 910COct 15, 20240.76×
  3. Ascend 950PRno date given0.51×
Company-reported

Roadmap (company-reported, Sept 2025): Ascend 950PR Q1 2026, 950DT Q4 2026, 960 Q4 2027, 970 Q4 2028; Atlas 950 SuperPoD of 8,192 Ascend 950DT chips in Q4 2026.

“Generally, we will follow a 1-year release cycle and double compute with each release.”

Huawei Connect 2025 keynote, Sep 18, 2025

China

Cambricon

  1. Siyuan 590Oct 31, 20240.26×

Ratings and release dates: Epoch AI, AI chip types (CC BY 4.0), Oct 19, 2026. Epoch gives ratings for Rubin and the Ascend 950PR without a release date.

Who owns the computing power

Five companies, most of the world's.

Epoch AI's estimates of the AI computing power each company had bought by the end of 2025, counted in H100s.

71%

held by Amazon, Google, Meta, Microsoft and Oracle together, up from 63% in early 2024.

Epoch AI, Apr 14, 2026

~5M

H100s' worth at Google, about a quarter of the world's total, mostly its own TPU chips.

Epoch AI, Apr 7, 2026

5%+

“Chinese companies collectively own just over 5% of the cumulative computing power” of leading AI chips, Epoch says of Chinese companies.

Epoch AI, Apr 6, 2026

Estimated computing power owned, end of 2025

  1. Google5.0M
  2. Microsoft3.4M
  3. Amazon2.4M
  4. Meta2.3M
  5. China (incl. smuggled)1.8M
  6. Oracle1.1M

In millions of H100-equivalents. Each figure is our sum of Epoch's middle estimates for that owner's chips by designer, so treat it as approximate. China's includes Epoch's estimate of smuggled chips (1.2M without them). Epoch AI, AI chip owners, May 12, 2026

The money

What's being spent.

Spending on buildings and equipment (capex), as the companies report it. Each counts it differently, so the figures shouldn't be added together.

Company-reported

Microsoft

$35.8bn in Q4 fiscal 2026

$115.9bn over the fiscal year.

Counted as: additions to property and equipment (cash flow statement); excludes finance leases. Microsoft FY26 Q4 press release, Jul 29, 2026

Company-reported

Amazon

$54.2bn in Q2 2026

$173.0bn over the past 12 months. Amazon says: “This increase primarily reflects investments in artificial intelligence.”

Counted as: purchases of property and equipment (gross, cash flow statement). Amazon.com Announces Second Quarter Results, Jul 30, 2026

Company-reported

Meta

$31.08bn in Q2 2026

Expects 2026 spending “to be in the range of $130-145 billion”.

Counted as: capital expenditures including principal payments on finance leases. Meta Reports Second Quarter 2026 Results, Jul 29, 2026

Company-reported

Nvidia's data center sales

$89.0bn in Q2 fiscal 2027, +117% on a year earlier

“Second-quarter revenue was $89.0 billion, up 18% from the previous quarter and up 117% from a year ago.”

Its outlook: “NVIDIA is not assuming any Data Center compute revenue from China in its outlook.”

NVIDIA Announces Financial Results for Second Quarter Fiscal 2027, Aug 26, 2026

The big projects

  • Stargate (OpenAI, SoftBank, Oracle, MGX) Announced as a new company intending to invest $500 billion over four years in AI infrastructure for OpenAI in the US, $100 billion immediately. “The Stargate Project is a new company which intends to invest $500 billion over the next four years” OpenAI, Announcing The Stargate Project · company-reported
  • Stargate sites tracked by Epoch Epoch lists 8 Stargate sites: Abilene (421 MW now, 843 MW projected Q4 2026), Shackelford (1,400 MW projected Q4 2028), Michigan (988 MW, end-2028), Milam (857 MW, Q4 2028), UAE (1,000 MW, ~2028), plus Lordstown, New Mexico and Wisconsin. Epoch AI, AI data centers (CC BY 4.0)
  • Project Jupiter, New Mexico (Stargate) Oracle sent a force majeure notice to the developer; it says the project remains on schedule for 2028. TechCrunch (citing Bloomberg)
  • AMD–Anthropic Partnership to deploy up to 2 gigawatts of AMD Instinct MI450 Series GPUs (title of AMD release). AMD press release · company-reported
  • Meta Hyperion, Louisiana Under construction; Epoch projects 1,632 MW IT power by Q1 2028 at $61.8bn capital cost. Epoch AI directory

Alphabet's and Oracle's latest figures aren't here yet because we couldn't reach their releases. Third-quarter results from all five are due in late October.

Electricity and water

The power bill, measured.

Data centers of every kind, not only AI, from the International Energy Agency and the US Department of Energy.

Measured · World · 2024

415 TWh

“Data centres accounted for around 1.5% of the world's electricity consumption in 2024, or 415 terawatt-hours (TWh).”

IEA, Energy and AI (Executive summary), 2025

Measured · Shares by region · 2024

US 45%

“The United States accounted for the largest share of global data centre electricity consumption in 2024 (45%), followed by China (25%) and Europe (15%).”

IEA, Energy and AI (Executive summary), 2025

Forecast · United States · to 2030

nearly half of US electricity demand growth

“In the United States, data centres account for nearly half of electricity demand growth between now and 2030.”

IEA, Energy and AI (Executive summary), 2025

Water

We haven't found national figures we can cite yet. These are two local ones, as reported.

Cape Town, South Africa

Over 4.4 billion litres a year for two proposed Equinix data centers (174 MW) (claim by campaign groups Housing Assembly and Foxglove, as reported).

Rest of World, Sep 17, 2026

Ceará, Brazil

Developer estimate of 30,000 litres a day for a planned TikTok data center, which the Anacé community says is too low.

Rest of World, Sep 8, 2025

Export controls

Who may buy which chips.

US rules on selling advanced AI chips abroad, newest first. Most lines summarize each rule's official title; follow the link for the rule itself.

  1. Nvidia's guidance for the quarter to October 2026 assumes no data center compute revenue from China.

    “NVIDIA is not assuming any Data Center compute revenue from China in its outlook.”

    NVIDIA, Q2 fiscal 2027 results

  2. BIS gives the United Arab Emirates more favorable treatment under export rules.

    Federal Register (BIS), doc 2026-14132

  3. BIS moves exports of Nvidia H200-class and less advanced chips (e.g. AMD MI325X) to China and Macau from a presumption of denial to case-by-case review, with conditions.

    “The Bureau of Industry and Security (BIS) is revising its license review policy for exports of certain semiconductors”

    Covers chips with TPP below 21,000 and total DRAM bandwidth below 6,500 GB/s that are commercially available in the US; exporter certifications required; Macau- or D:5-headquartered entities stay under presumption of denial. Effective 2026-01-15.

    Federal Register (BIS), doc 2026-00789

  4. BIS adds and revises Entity List entries.

    Federal Register (BIS), doc 2025-17893

  5. US imposes new rules to curb sales of chip design software to China.

    TechCrunch · headline only

  6. The US government tells Nvidia a license is needed to export its H20 chips to China; Nvidia takes a $4.5 billion charge.

    “On April 9, 2025, NVIDIA was informed by the U.S. government that a license is required for exports of its H20 products into the China market.”

    NVIDIA, Q1 fiscal 2026 results

  7. BIS adds due-diligence measures for advanced computing chips (amended again 2025-02-14).

    Federal Register (BIS), doc 2025-00711

  8. BIS publishes the 'Framework for Artificial Intelligence Diffusion', setting worldwide license rules for advanced AI chips.

    Federal Register (BIS), doc 2025-00636

  9. BIS adds foreign-produced direct product rules and tightens advanced computing and chipmaking controls, with a same-day Entity List rule (doc 2024-28267).

    Federal Register (BIS), doc 2024-28270

  10. BIS creates a Data Center Validated End User authorization for approved data centers abroad.

    Federal Register (BIS), doc 2024-22587

  11. BIS publishes updates and corrections to the advanced computing rules.

    Federal Register (BIS), doc 2024-07004

  12. BIS updates the advanced computing chip rules (the October 2023 update), alongside a separate rule on chipmaking equipment (doc 2023-23049).

    Federal Register (BIS), doc 2023-23055

  13. BIS extends the October 2022 controls to Macau.

    Federal Register (BIS), doc 2023-00888

  14. BIS publishes its first rule on advanced computing chips, chipmaking items and supercomputer end uses, with Entity List changes.

    Federal Register (BIS), doc 2022-21658

China's own responses, such as limits on buying Nvidia chips and on exporting rare earths, aren't here yet: we couldn't reach a source we trust for them.

Local fights

Not in my backyard.

Where towns, states and communities have pushed back on AI data centers, or let them through.

policy change

Amazon (US-wide)

Amazon responds to data center backlash and says it no longer uses non-disclosure agreements.

TechCrunch, Oct 3, 2026 · headline only

delayed / contested

New Mexico, US (Project Jupiter, Stargate)

Residents and environmental groups oppose the campus; pipeline permits were repeatedly denied and an air permit is pending (state deadline 23 Nov); Oracle sent a force majeure notice.

“The notice would allow Oracle to delay payments should the facility miss its 2028 target to come online.”

TechCrunch (citing Bloomberg), Sep 24, 2026

tally

United States (national)

Data Center Watch counts $68 billion of projects disrupted by local opponents in Q2 2026.

“Data center projects worth $68 billion were disrupted by local opponents in the second quarter of 2026”

TechCrunch, Sep 22, 2026

audits ordered

Texas, US

Gov. Greg Abbott orders the PUCT and ERCOT to audit all new data center projects (power and water demand, noise, tax incentives, ownership).

“Governor Greg Abbott announced Monday that all new data center projects will need to be audited”

TechCrunch, Aug 4, 2026

legal challenge

Cape Town, South Africa

Housing Assembly and Foxglove file a legal challenge against two proposed Equinix data centers (174 MW), asking the Human Rights Commission to investigate and seeking a national moratorium.

“A massive data center is trying to jump the queue and take our land, water, and energy.”

Rest of World, Sep 17, 2026

lawsuit; turbines to be removed by July 2027

Memphis, Tennessee / northern Mississippi, US

SpaceX says it will remove the unpermitted gas turbines powering xAI's Colossus data centers, which the NAACP and Southern Environmental Law Center sued over, as it moves to a permanent gas plant.

“The turbines won’t be completely removed until July 2027, though.”

TechCrunch, Jul 31, 2026

paused

New York State, US

Gov. Kathy Hochul signs an executive order pausing new state permits for data centers of 50 MW or more until an environmental review is finished (expected about a year).

“Progress shouldn’t arrive with a higher utility bill, deleted water supply, or noise pollution.” Kathy Hochul

TechCrunch, Jul 14, 2026

moratorium vetoed

Maine, US

Gov. Janet Mills vetoes LD 307, which would have been the first statewide moratorium on new data centers (to 1 Nov 2027).

“Maine Governor Janet Mills has vetoed a bill that would have temporarily brought to a halt permits for new data centers.”

TechCrunch, Apr 25, 2026

protests

Andhra Pradesh, India

Farmers and the Human Rights Forum contest land acquisition and incentives (about $2.4bn over 20 years) for Google's $15 billion data center campus.

“The proposed sites for the data-center campus have been earmarked through opaque land-pooling and acquisition mechanisms,” Human Rights Forum

Rest of World, Apr 13, 2026

financed / building

Bruyères-le-Châtel, near Paris, France

Mistral AI raises $830 million in debt to set up a data center there, aiming to start operating by Q2 2026 (a go-ahead, not a fight).

“Mistral aims to start operating the data center by the second quarter of 2026.”

TechCrunch, Mar 30, 2026

complaint filed

Ceará, Brazil

The Anacé Indigenous community files a complaint with federal authorities to halt a planned $10 billion TikTok data center it says sits on ancestral land.

Rest of World, Sep 8, 2025

Fights in Europe and the UK aren't covered yet. Everything on this page was read at its source on Oct 19, 2026. Spot a mistake? Tell us.